Built for every trade

HVAC takeoff software for ductwork, diffusers and units

Mechanical and HVAC takeoffs count the units, grilles, dampers and controllers and measure the ductwork and pipe between them: rigid and flexible duct, refrigerant pipe and condensate drains. TrueScale™ counts and measures each on the mechanical layout, floor by floor.

Start free trial 30 days, every feature, no card

What mechanical and HVAC contractors measure, and why

  • Rigid and flexible duct as separate runs, because they are different materials at different rates.
  • Supply and return grilles as counts, because each is a fitting, a connection and a point to balance.
  • Split, ducted and outdoor units, zone dampers, controllers, exhaust fans and roof cowls as counts.
  • Refrigerant pipe and condensate drains as runs.

The Mechanical tool set

13 tools, from Tool Shed > Trade sets... > Mechanical:

ToolMeasuresStarter spec
Duct runlengthFlexible duct 200
Supply ventscountSupply grille
Return ventscountReturn grille
Split systemscountSplit system 7 kW
Exhaust fanscountExhaust fan
Rigid duct runlengthRigid duct 300 x 200
Refrigerant pipe runlengthRefrigerant pipe pair
Condensate drain runlengthCondensate drain 20 mm
Ducted unitscountDucted unit 14 kW
Outdoor unitscountOutdoor unit
Zone damperscountZone damper
ControllerscountWall controller
Roof cowlscountRoof cowl

Worked example

Worked example: Harbour Works Offices

Sheet ME.01, the mechanical (HVAC) layout for the typical office floor at 1:100. It stands for level 1 and level 2.

MeasuredSheetQuantity
Supply diffusersME.0117 per floor, 34 for two floors
Rigid supply duct 600 x 300 along the corridorME.0123.20 m per floor, 46.40 m
Flexible branch duct to each diffuser, as drawnME.01105.60 m per floor, 211.20 m
Air handling unitsME.01one per floor, from the sheet notes

The sheet notes call for a VAV system, an air handling unit on each floor and ductwork insulated to R1.0.

The branches are drawn straight from the main to each diffuser. Flexible duct in a ceiling is longer than that, so the drawn length is a starting point.

A fictional demo project, drawn to scale and measured in TrueScale.

Start free trial 30 days, every feature, no card

Common mechanical takeoff mistakes

  • Counting a typical floor once. ME.01 stands for two floors. Count it once, then double it.
  • One size for the whole main. Ducts get smaller along a run. Split a main into one run per size so each size has its own total.
  • Taking schematic branches as real lengths. Branches drawn as straight lines are shorter than the duct you install. Add an allowance.
  • Leaving out insulation and supports. Insulated ductwork and its hangers are priced with the duct. The duct lengths drive both.

Standards and the NCC

Mechanical ventilation is designed to AS 1668.2 and fire and smoke control in air handling systems to AS 1668.1. Cooling towers and water systems are designed for microbial control under AS/NZS 3666.1, and energy efficiency, including duct insulation, comes from Section J of the NCC.

Mechanical takeoff questions

How do I measure ductwork from a mechanical plan?

Use Rigid duct run for sheet metal duct and Duct run for flexible duct, and click along each route. Make a copy of a tool for each duct size so each has its own total.

Can I count diffusers and grilles?

Yes. Supply vents and Return vents are count tools, each with its own symbol.

Does the set include split systems and outdoor units?

Yes. Split systems, Ducted units, Outdoor units, Zone dampers and Controllers are counts, with Refrigerant pipe run and Condensate drain run for the pipework.

Duct metres and diffuser counts into an Excel quote

Pay once. Own it

One licence has every feature, the Estimate panel and Excel links included. Pay once, own your licence, and take off on TrueScale for Mac too.

Mac: Apple silicon (M1 or newer), macOS 14 or later. Printing, OCR, email, spell check and Link for Excel aren't on Mac yet. What's different on Mac